ITE, İRAN-TÜRKİYE-AVRUPA DOĞALGAZ BORU HATTI PROJESİ, TÜRKİYE KISMI MÜHENDİSLİK İŞLERİ İÇİN, MÜŞAVİRLİK HİZMETLERİ
Project Name
ITE,IRAN-TURKEY-EUROPE Natural Gas Pipeline Project ,Engineering Services for Turkish Section & Consultancy Services
Client
TURANG Transit Taşımacılık A.Ş.
Contractor
Ener İnşaat Savunma Sistemleri Sanayi ve Ticaret A.Ş
Date of Contract
01.02.2012
Project Duration
22 Months
Project Description
Owner’s Engineering Services for ITE (Iran- Turkey- Europe) 56'' Natural Gas Pipeline Project which is 5000 km long from İran to Germany , 1780 km Turkish section were carried out on behalf of Turang Transit Taşımacılık A.ş in 22 months.ITE Natural Gas Pipeline Project’s route corridor passes through the provincial borders of Ağrı, Erzurum, Erzincan, Gümüşhane, Sivas, Kırşehir, Yozgat, Kırıkkale, Ankara, Eskişehir, Kütahya, Bilecik, Bursa, Balıkesir, Çanakkale, Tekirdağ, Edirne, respectively.
P/L Class
Natural Gas
Design Pressure
90 bar
P/L Diameter
56''
P/L Route
1.780 km length (17 km. offshore Marmarian Sea crossing)
Capacity
35 billion m3/year
Design Standart
ASME
Compressor Stations
7 No's
Leak and Intrusion Detection System
Set
Line Valve Stations
48 No's
Pig Stations
10 No's
Metering Station
1 No
Owner's Engineering Service has given for
Preliminary Engineering Services Geodesy /Photogrammetry /Geology/Geotechnical Studies Project Engineering Services Geographical Information System (G.I.S) EIA, Expropriation and Land Valuation Studies